Maitland Gaol redevelopment

Project Status

Complete
Maitland Gaol Development and Site Master Plan adopted by Maitland Council
September 2020
Complete
Tower Experience funding announced
August 2021
Complete
Over $10 million of shared State and Federal funding announced
January 2022
Complete
Development application for Tower Experience approved
August 2022
Complete
Tower Experience tender awarded, commencement of construction
Autumn 2023
Complete
Early works commence on new Activity Hub
April to June 2023
Complete
Tower Experience practical completion and open to the public
November 2023
Current
Development application submitted for accommodation and restaurant/cafe
September 2024
Upcoming
Development application outcome received
July 2025
Upcoming
Tender process (three months)
August 2025
Upcoming
Commencement of construction (pending approved DA)
December 2025
Upcoming
Construction complete
December 2026

Major redevelopment works at Maitland Gaol will transform the historic site into a vibrant precinct and iconic destination for the Hunter, driven by its unique heritage, connection to the community and innovative experiences.

Through NSW Government, Australian Government and Council funding, over $11.7 million has been allocated for this stage of the Maitland Gaol redevelopment – which includes investment in boutique accommodation, a new activity hub, innovative interpretation of the site and the provision of new event infrastructure. 

Access to the Gaol site will be opened up through the existing walls, allowing for improved community access to the activity hub and internal courtyard area. 

In December 2023, one of the site’s storied towers was fitted with a spiral staircase, opening up access to the guardtowers and gantries, courtesy of $129,000 in grant funding via Destination NSW.

The new tower experience offers patrons of Maitland Gaol a new perspective and interpretation of an old site. 